INTRODUCTION THE CIVIL WORKS

BACK

Sirius will consist of a set of electron accelerators for experimental stations, called beamlines, and a building that will house all this complex. With 68,000 square meters, the building will be among the most sophisticated civil works ever built in the country.

 

Electron Accelerators with the dimensions and technical specifications for the new Synchrotron Light Source Sirius and its beamlines require high-performance buildings and facilities, called critical-mission buildings, in which features such as stability (dimensional, thermal and vibrational) and maintenance availability and viability are essential. This is the building that will house the Sirius, one of the most advanced constructions ever built in the country.

 

This building is being installed adjacent to the CNPEM campus, located in Campinas, Sao Paulo, in an extension of land expropriated by the State Government of São Paulo for the construction of Sirius.

A DISTINCTIVE BUILDING

 

With 68,000 square meters of built area, the main Sirius building will have four floors with capacity for up to 620 people, including employees and visitors. The predominantly circular shape of the building is a result of the geometry of the main accelerator (storage ring), where electrons are stored and synchrotron light is produced.

 

It will house the three accelerators of electrons and up to 40 beamlines, six of which are considered long, with lengths ranging from 100 to 150 meters. The building and its implementation are designed so that two extra-long beamlines can be built in the future with experimental stations up to 250 meters away.

 

In addition to the experimental area, this building has in its interior areas for utilities and sources of current to the accelerators as well as support laboratories, data centers, operation and control room, living areas and offices.

STABILITY IN NUMBERS

 

One of the biggest challenges of Sirius is the stability (dimensional, thermal and vibrational). At Sirius, each electron beam, which in some segments of the accelerators is only 1.5 micrometers in vertical size, four times smaller than a red blood cell, must follow a circular path of 500 meters in circumference, 600,000 times every second for hours without oscillating more than one tenth its size.

 

CONSTRUCTIVE ASPECTS

 

The structure of the building will be made of cast-in-place reinforced concrete and all its floors, including the ground floor, will also be built in reinforced concrete slabs. Thus, the structure will present great rigidity, reducing the transmission of vibration from the action of the wind, the movement of people and the operation of equipment and facilities.

 

Both the foundation and the floor of the experimental hall and of the shielding of the accelerators are separated from the rest of the floors of the buildings in order to avoid differential settlements, distortion and propagation of vibrations, whether generated internally or from external environments.

 

The roofing will be in aluminium conical seam panels with insulation for low thermal transmittance, ensuring the highly stable temperature control required by the environment.

TIMETABLE AND STATUS

In 2013, an extension of the land adjacent to CNPEM was expropriated by the State Government of São Paulo for the construction of Sirius. The earthwork was started in that same year and completed in 2014. On December 19th, 2014, the contract was signed with the construction company and the cornerstone of the Civil Works was laid.

 

In January 2015, the construction of the building for the new Synchrotron Light Source were effectively started. During the year, the first and part of the second phase of the planned schedule was concluded, including: the implementation of the construction site and temporary infrastructure; the execution of the foundation of the main building, of the Engineering, Compressors and Generators Areas, and part of long beamlines; the partial implementation of the superstructure of the main building and the construction of the metal structure of the roof of the main building. At the end of 2015, almost 20% of the civil works were complete.

 

The Civil Works are expected to last a total of 40 months.

PHOTOS

Sirius: Obras Civis / Civil Works 1



Português:
Status das Obras Civis em 9 de Setembro de 2013.

English:
Status of the Civil Works on September 9th, 2013.

Sirius: Obras Civis / Civil Works 2



Português:
Status das Obras Civis em 18 de Novembro de 2013.

English:
Status of the Civil Works on November 18th, 2013.

Sirius: Obras Civis / Civil Works 3



Português:
Status das Obras Civis em 10 de Março de 2014.

English:
Status of the Civil Works on March 10th, 2014.

Sirius: Obras Civis / Civil Works 4



Português:
Status das Obras Civis em 20 de Julho de 2015.

English:
Status of the Civil Works on July 20th, 2015.

Sirius: Obras Civis / Civil Works 5



Português:
Status das Obras Civis em 6 de Outubro de 2015.

English:
Status of the Civil Works on October 6th, 2015.

Sirius: Obras Civis / Civil Works 6



Português:
Status das Obras Civis em 16 de Fevereiro de 2016.

English:
Status of the Civil Works on February 16th, 2016.

Sirius: Obras Civis / Civil Works 7



Português:
Status das Obras Civis em 24 de Março de 2016.

English:
Status of the Civil Works on March 24th, 2016.

Sirius: Obras Civis / Civil Works 8



Português:
Status das Obras Civis em 28 de Abril de 2016.

English:
Status of the Civil Works on April 28th, 2016.

Sirius: Obras Civis / Civil Works 9



Português:
Status das Obras Civis em 24 de Junho de 2016.

English:
Status of the Civil Works on June 24th, 2016.

Sirius: Obras Civis / Civil Works 10



Português:
Status das Obras Civis em 19 de Julho de 2016.

English:
Status of the Civil Works on July 19th, 2016.

Sirius: Obras Civis / Civil Works 11



Português:
Status das Obras Civis em 29 de Agosto de 2016.

English:
Status of the Civil Works on August 29th, 2016.

Sirius: Obras Civis / Civil Works 12



Português:
Status das Obras Civis em 30 de Setembro de 2016.

English:
Status of the Civil Works on September 30th, 2016.

Sirius: Obras Civis / Civil Works 13



Português:
Status das Obras Civis em 30 de Outubro de 2016.

English:
Status of the Civil Works on October 30th, 2016.

Sirius: Obras Civis / Civil Works 14



Português:
Status das Obras Civis em 23 de Novembro de 2016.

English:
Status of the Civil Works on November 23rd, 2016.

Sirius: Obras Civis / Civil Works 15



Português:
Status das Obras Civis em 3 de Janeiro de 2016.

English:
Status of the Civil Works on January 3rd, 2016.